
Industrial solutions
C&I energy storage solutions built around the operating problem.
Start with measured load behavior, generation, critical loads and the electrical boundary; then compare documented cabinet, container, hybrid and DC storage platforms.
Application first
One C&I BESS portfolio. Different operating priorities.
C&I energy storage solutions behave differently depending on dispatch logic, reserve requirement, PCS sizing and the responsibility boundary. Buyers, EPCs and integrators should define the operating target and required project evidence before comparing equipment.
Commercial applications
Translate each C&I energy storage use case into engineering inputs.
Each application changes the power-to-energy ratio, controls, acceptance tests and project evidence.
Peak shaving and load shifting
Use interval load data to define discharge power, usable capacity, dispatch window, reserve and demand-control logic.
Solar self-consumption
Coordinate PV generation, export limits, daytime charging, evening discharge and transformer headroom.
Microgrid and backup power
Define critical loads, transfer behavior, islanding, autonomy, generator support and restart sequence.
EV charging plus storage
Manage short charger peaks, transformer relief, simultaneous charging and battery replenishment strategy.
PV-storage-diesel hybrid
Use the integrated 100 kW / 233 kWh platform where PV is primary, storage smooths supply and diesel remains backup.
Data-center UPS backup
Define DC voltage window, UPS interface, autonomy and redundancy around the 219.24 kWh sodium-ion DC cabinet.
Application map
Choose a starting platform—not a final answer.
Each recommendation must be validated against project voltage, load type, ambient derating, local code and delivery responsibility.
| Solution | Primary input | Starting platform | Acceptance focus |
|---|---|---|---|
| Peak shaving | 15-minute or finer load curve | 105–250 kW cabinet or MW container | PCS kW, dispatch window and EMS test |
| Solar self-consumption | PV generation, export rule and load curve | 400 V cabinet or project-scale container | Power-flow, meter and communication test |
| Microgrid backup | Critical load, outage duration and generator data | 100/233 hybrid or engineered BESS | STS/ATS, islanding and scenario test |
| EV charging | Charger power, utilization and transformer limit | Cabinet for distributed site; container for hub | Peak-demand and replenishment simulation |
| PV-storage-diesel | PV array, weak-grid data and generator rating | 100 kW / 233 kWh hybrid cabinet | Source priority, transfer and restart test |
| Data-center UPS | UPS DC window, autonomy and redundancy target | 219.24 kWh sodium-ion DC cabinet | DC interface, alarm and discharge test |
Control hierarchy
Write the source priority before sizing equipment.
For grid, PV, storage, charger and generator projects, the operating sequence determines the PCS duty, reserve, transfer devices and communications.
Solution design guides
Move from the application to measured sizing inputs.
Use measured demand, duration and operating priorities before selecting the final cabinet or container configuration.
C&I energy storage system use cases
Compare peak shaving, solar, backup and industrial microgrid scenarios with their starting kW, kWh and control inputs.
Read guidePeak shaving battery sizing
Translate interval load data, target demand and peak duration into kW and kWh.
Read guideLoad profile for a BESS quotation
Prepare interval demand, tariffs, PV, generators, critical loads and operating schedules.
Read guideSolution questions
Questions buyers ask before selecting a platform.
These answers narrow the architecture but do not replace project engineering.
Can one cabinet support both peak shaving and backup?
Yes, but usable energy must be divided between daily dispatch and protected reserve. The load priority, transfer device and minimum reserve SOC must be written into the control philosophy.
When should a project move from a cabinet to a container?
Move toward a container when power or energy exceeds the cabinet range, when multiple battery strings and a step-up interface are required, or when a centralized service and fire layout is preferred.
Is the 100 kW / 233 kWh system a complete off-grid plant?
It integrates the battery, PCS, 100 kW DCDC/MPPT and 200 kW STS, with an interface for an external diesel generator. PV array, generator, switchgear, transformer and site works must still be confirmed in the project scope.
Can the sodium-ion cabinet replace any UPS battery bank?
No. Its 216-504 Vdc operating window, 417.6 V rated voltage, autonomy, fault current, UPS charging behavior and redundancy architecture must match the selected UPS.
What should an EPC or integrator request from a C&I BESS supplier?
Request the project datasheet, single-line diagram, equipment and responsibility boundary, PCS and battery limits, protection assumptions, protocol map, certification list, FAT plan, delivery scope and commissioning responsibilities.
Turn the operating target into a quotation-ready BESS scope.
Send the site country, grid voltage, interval load data, PV or charger profile, critical-load list, target kW/kWh and responsibility boundary.
